20th October- 30th November (6 weeks)
Planned Work
Designated Map for Machinary- to minimise damage to the course
20th October- 2nd November
Chris Poulton (Course Director) will make a start on the preparatory work so the Contrators can achieve more when on site.
Updates will be given each Monday of the Project, showing the plan for the week, photos and what has been achieved last week.
3rd November- Week 1 (Contractors Arrive)
Plan:
Achieved so far:
Photos: